The best technical solution for a critical DSP step was found in the ZETA TechCenter. Experiments were carried out on a pilot scale to develop a drainage strategy and to overcome a specific problem of the breakthrough of the aqueous phase through the viscous product-containing phase. The planning and production of the separation plant took place following the feasibility studies.

Facts

- Product/Service Category:
Downstream processing - Project Duration: 9 months
- Project Country: Austria / Netherlands
- Scope of Supply:
TechCenter Concept studies
Basic / Detail Engineering
Automation
Fabrication
Installation
Start up
Qualification

Contact: Andreas Glössl
Dir. Business Line Customised Systems
We look forward
to hearing from you!