ZETA acted as the general planner for all essential project planning phases for the expansion of the basic fractionation of blood plasma in the inner courtyard of an existing plant. ZETA was also responsible for realizing the project and supporting the construction management. The process of plasma processing was always the focus. The ZETA scope also included the planning of additional infrastructure.

Facts

- Project Duration: 42 months
- Project Country: Austria
- Scope of Supply:
Process Development Support / Scale Up
Concept Design
Basic Engineering
Detail Engineering
Procurement
Construction
Automation
Qualification