Our customer was planning an expansion and separation of sections of an existing production plant in Switzerland. This required major modifications to the existing systems in the buildings, in the outside areas and also in the storage tanks. Construction of a new building was also planned.

  • Product/service category: On-Site Installation

  • Challenge of the project: The customer demanded a tight timetable for the modification of the existing production plant. In the course of creating the new systems, the process design for the new production was also revised.

  • ZETA solutions: The demanding timeline required flexible personnel planning and close cooperation with the customer.

  • Scope of supply: work preparation, planning of temporary rearrangement of connections, material management, construction site management, installation, documentation, IQ preparation, support for commissioning

  • Main equipment: 12,000 m of pipework, 8,000 pipe fittings, 2,000 valves

  • Project country: Switzerland

  • Completion time: 15 months
 
 